Project Profile

“Horst Construction has been working with West Pharmaceutical on a variety of industrial and controlled environment design-build projects in Pennsylvania, North Carolina, and Florida over the last nine years; their knowledge of our high quality standards and technical requirements were evident throughout the design and construction of the central chiller project.”

“The central chiller plant building addition was the largest piece of the project; however, Horst worked in every section of the plant in order to incorporate the new central chilled water distribution loop.  The clear and well planned coordination throughout the project enabled everyone at West to plan accordingly and the project to be completed on schedule while minimizing disruptions.”

David Onzik, Senior Project Manager
West Pharmaceutical Services, Inc.
Kinston, NC

West Pharmaceutical Services, Inc., Central Chiller Plant

Owner: West Pharmaceutical Services, Inc.
Location: Jersey Shore, PA
Architect: Cornerstone Design Architects
Engineer: DME Alliance, Inc.

The design-build team collaborated to design and build a compact multi-story facility to provide 1800 tons of cooling capacity and to provide one central chiller plant in lieu of 4 separate existing chiller plants throughout the production areas.  The project required significant coordination to allow operations to continue without interruption throughout the construction project.

Project Type: Addition
Services: Design-Build
Size: Addition – 2,463 square feet, Chiller Supply/Return Piping for 101,800 square feet facility
Features:
  • Designed and constructed a compact multi-story facility to provide 1800 tons of cooling capacity to provide one central chiller plant in lieu of 4 separate existing chiller plants throughout the production areas
  • Preconstruction/Lead Design Meetings/Design Coordination
  • Provided value engineering options and cost analysis
  • 2-story structural steel frame with insulated steel siding
  • 2 New Chillers, 2 New Cooling Towers, Pumps, and all operated with Variable Frequency Drives controlled by Siemens energy management system
  • Structural steel added to the existing building during plant operations to support the supply and return chilled water lines from 12” to 4” in size
  • Entire plant changeover to the central chiller system was achieved without the loss of revenue for the client
Awards:
  • ABC Keystone – Excellence in Construction – Award of Excellence
Project Type: Addition